Child Development - Remodel Room 35 |
|
Project Overview |
The scope of the Child Development Remodel Room 35 includes demolition of existing control room, construction of small training rooms and an observation room. New construction will include new flooring, new ceiling tile/grid/lighting, install of A/V recording equipment, and additional cooling for A/V equipment room.
|
Schedule |
No |
|
End Date |
|
Task |
1 |
|
2/16/2009 |
|
Educational Meeting & Site Walk
|
2 |
|
3/02/2009 |
|
Submittals Due
|
3 |
|
3/04/2009 |
|
UMN Identifies Potential Best Value
|
4 |
|
3/05/2009 |
|
Pre Award Kick Off Meeting
|
5 |
|
3/11/2009 |
|
Pre-Award meeting
|
6 |
|
3/12/2009 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
RSP Architects |
Estimated Budget: |
|
$22,000 |
Awarded Cost: |
|
$22,000 |
Awarded Duration: |
|
45 days |
Scope of Work: |
|
Demolition of existing control room |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
Closeout Status |
Vendor met proposed schedule: |
|
Yes |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
10 |
| Final rating of contractor (10 max): |
|
10 |
|
|