University of Minnesota

University of Minnesota
Child Care HVAC Project

Project Overview
Consists of replacing the existing on grade HVAC system including infilling abandoned under slab ductwork and installing new roof HVAC units and associated above ceiling duct work
Schedule

No
 
End Date
 
Task
1
 
9/22/06
 
Educational Meeting
2
 
11/07/06
 
Site Walk
3
 
11/21/06
 
Submittals Due (Proposal, RA Plan, EEO)
4
 
11/28/06
 
UMN Identifies Best Value
5
 
11/28/06
 
Pre Award Kick Off Meeting
6
 
12/13/06
 
Pre Award Meeting
7
 
12/14/06
 
Anticipated Date of Award

Bidding / Proposal Information
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG.
Award Information
Vendor Name:
  Cool Air Mechanical
Estimated Budget:
  $650,000
Awarded Cost:
  $446,100
Awarded Schedule
  144 days
Scope of Work:
  Replace HVAC Units

For detailed award information, click here (pptico XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)

For a complete list of all project risks, click here (pptico DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.
Closeout Status
Vendor met proposed schedule:
  Yes
Vendor met proposed cost:
  Yes
Vendor met purposed quality/customer satisfaction:
  Yes
Final customer rating of PIPS (10 max):
  10
Final rating of contractor (10 max):   9.88

If you have any questions please email John Savicky at John.Savicky@asu.edu
Contact Us