Centennial Hall New Student Kitchen

Project Overview
The scope of work is detailed in the drawings dated 10/1/09. In addition to the drawings the Contractor is responsible for:
• All materials, equipment, hardware, material staging, garbage removal, housekeeping, permits, inspections, schedule, and closeout / punch list unless otherwise noted.
• Clean up at the end of each work day.
• Coordination of all work involving University Services including, but not limited to: Facilities Management District employees, Hazardous Materials and Networking & Telecommunications Services (NTS).
• Coordinating their construction schedule with building occupants.
o Centennial Hall has a noise restriction prior to 9:00 AM.
• Parking and Security during the project.
• Supplying and installing electrical cords for all appliances.
• Any Fire Alarm programming/testing deemed necessary for this project.
• Uncrating, setting in place and installation of Owner provided appliances.
o Owner will have appliances delivered to the Centennial Loading Dock, Contractor to move from dock to construction site.
• Uncrating, setting in place and installation of Owner provided furniture.
o Owner will have furniture delivered to the Centennial Loading Dock, Contractor to move from dock to construction site.
• Signage and installation.

Other items of note:
• Contractor and sub-contractors must be properly identified by work attire with their logo or identification badge.
• Any work performed in areas where hazardous materials are present must be performed by trained, certified personnel. Owner reserves the right to request proof of training and certification.


Schedule

No   End Date   Task
1   10/07/09   Educational Meeting & Site Walk
2   10/20/09   Submittals Due (Proposal, RA Plan, EEO)
3   10/26/09   UMN Identifies Potential Best Value
4   10/28/09   Pre Award Kick Off Meeting
5   11/02/09   Pre Award Meeting
6   11/05/09   Anticipated Date of Award

Award Information
Vendor Name:
  M.A. Mortenson Construction
Estimated Budget:
  $92,000
Awarded Cost:
  $73,568
Awarded Duration:
  35 days
Scope of Work:
  Construction of Kitchen

For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)

For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.
Closeout Status
Vendor met proposed schedule:
  Yes
Vendor met proposed cost:
  Yes
Vendor met purposed quality/customer satisfaction:
  Yes
Final customer rating of PIPS (10 max):
  10
Final rating of contractor (10 max):   9.9