University of Minnesota
Carlson Plaza Remediation |
|
Project Overview |
The intent of this project is to provide a design to correct failing concrete walking surfaces, reduce the amount of concrete surface, increase the landscape areas, and minimize the damage/maintenance to the below-grade occupied areas. Construction to be delivered by the PIPS proposal process. Project goals, objectives, type of work, delivery method, etc.
|
Schedule |
| 1 |
|
09/17/09 |
|
Educational Meeting & Site Walk |
| 2 |
|
10/01/09 |
|
Submittals Due (Proposal, RA Plan, EEO) |
| 3 |
|
10/19/09 |
|
Interviews |
| 4 |
|
10/23/09 |
|
UMN Identifies Potential Best Value |
| 5 |
|
10/27/09 |
|
Pre Award Kick Off Meeting |
| 6 |
|
11/10/09 |
|
Pre Award Meeting |
| 7 |
|
11/12/09 |
|
Anticipated Date of Award |
|
Award Information
This project has not been awarded. Project award information will be made available once an award has been made. Please check back at a later date.
|
Award Information |
Vendor Name: |
|
Conway Schulte Architects |
Estimated Budget: |
|
$18,000 |
Awarded Cost: |
|
$46,299 |
Awarded Duration: |
|
33 days |
Scope of Work: |
|
To provide a design to correct failing concrete walking surfaces |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
Closeout Status |
Vendor met proposed schedule: |
|
Yes |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
10 |
| Final rating of contractor (10 max): |
|
9.6 |
|
|
|
|
 |