Bell Museum – Carpenter Shop – Room S7

Project Overview
This project includes removing all existing wood walls, and three existing doors to Room S7 and installing new gypsum board walls and fire rated doors, to match size of existing door openings. All new surfaces shall be painted. The general contractor will remove existing storage along these walls during construction, and will need to return these items to original location after construction.
Schedule

No
 
End Date
 
Task
1
 
10/12/07
 
Educational Meeting & Site Walk
2
 
10/25/07
 
Submittals Due (Proposal, RA Plan, EEO) 
3
 
10/31/07
 
UMN Identifies Best Value
4
 
11/07/07
 
Pre Award Kick Off Meeting
5
 
11/21/07
 
Pre Award Meeting
6
 
11/27/07
 
Anticipated Date of Award


Bidding / Proposal Information
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG.
Award Information
Vendor Name:
  Sheehy Construction
Estimated Budget:
  $40,000
Awarded Cost:
  $44,400
Awarded Schedule:
  35 days

For a complete list of all project risks, click here (pptico DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.
Closeout Status
Vendor met proposed schedule:
  Yes
Vendor met proposed cost:
  Yes
Vendor met purposed quality/customer satisfaction:
  Yes
Final customer rating of PIPS (10 max):
  10
Final rating of contractor (10 max):
  9.4

If you have any questions please email John Savicky at John.Savicky@asu.edu