Barn Cleaner Renovations

Project Overview
Large Animal Holding Manure Handling Systems Upgrades, Waste Drainage and Cleaning Improvement

This project will take place at the Large Animal Holding Building #417, located at 1907 Carter Ave., St. Paul, MN 55108
Schedule

No
 
End Date
 
Task
1
 
1/18/08
 
Educational Meeting & Site Walk
2
 
2/05/08
 
Submittals Due (Proposal, RA Plan, EEO)
3
 
2/26/08
 
UMN Identifies Potential Best Value
4
 
3/04/08
 
Pre Award Kick Off Meeting
5
 
3/18/08
 
Pre Award Meeting
6
 
3/20/08
 
Anticipated Date of Award


Bidding / Proposal Information
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG.
Award Information
Vendor Name:
  LS Black Constructors, Inc.
Estimated Budget:
  $225,000
Awarded Cost:
  $269,000
Awarded Schedule:
  80 days
Scope of Work:
  Animal Holding Manure Handling Systems Upgrade, Waste Drainage &
Cleaning Improvement

For a complete list of all project risks, click here (pptico DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.