University of Minnesota
Akerman Hall Hangar Renovation |
|
Project Overview |
The University is requesting Proposals for services for a Design Build contract for the design and renovation of the Hangar area at Akerman Hall and installation of a fire alarm sprinkler system for the entire Akerman Hall and Mechanical Engineering buildings.
|
Schedule |
| 1 |
|
8/27/2009 |
|
Educational Meeting & Site Walk |
| 2 |
|
9/11/2009 |
|
Submittals Due (Proposal, RA Plan, EEO) |
| 3 |
|
10/07/2009 |
|
UMN Identifies Potential Best Value |
| 4 |
|
10/14/2009 |
|
Pre Award Kick Off Meeting |
| 5 |
|
10/27/2009 |
|
Pre Award Meeting |
| 6 |
|
10/30/2009 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
M.A. Mortenson |
Estimated Budget: |
|
$219,000 |
Awarded Cost: |
|
$219,000 |
Awarded Duration: |
|
87 days |
Scope of Work: |
|
Design and renovation of hanger area |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|