University of Minnesota
Akerman Hall - Office Renovations |
|
Project Overview |
Project consists of Renovation of office and student lounge areas. Work includes new doors, walls, carpet, painting, casework, mechanical and electrical modifications as per intention of drawings which will be distributed at the site meeting at Akerman Hall 110 Union Street SE, Minneapolis campus.
|
|
Schedule |
No |
|
End Date |
|
Task |
1 |
|
12/15/06 |
|
Educational Meeting & Site Walk
|
2 |
|
1/09/07 |
|
Submittals Due
|
3 |
|
1/09/07 |
|
UMN Identifies Best Value
|
4 |
|
1/12/07 |
|
Pre-Award Kickoff Meeting
|
5 |
|
1/29/07 |
|
Pre-Award Meeting |
6 |
|
1/31/07 |
|
Anticipated Date of Award |
|
Bidding / Proposal Information |
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG. |
|
Award Information |
Vendor Name: |
|
PCL Construction |
Estimated Budget: |
|
$325,000 |
Awarded Cost: |
|
$323,000 |
Awarded Schedule: |
|
59 days |
Scope of Work: |
|
Renovations of office and student lounge |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
Closeout Status |
Vendor met proposed schedule: |
|
Yes |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
10 |
| Final rating of contractor (10 max): |
|
10 |
|
|