University of minnesota
AHC Combined Security |
|
Project Overview |
Installation of Video Surveillance and Card Access System. Contractor will be responsible for all materials, equipment, hardware, labor, garbage removal, housekeeping, permits, inspections, schedule, and closeout/punchlist unless otherwise noted. Contractor will be expected to coordinate all work involving Networking & Telecommunications Services (NTS) and Department of Central Security (DCS). Contractor will be responsible to coordinate their work schedule with building occupants. Parking and security during the project is the responsibility of the Contractor.
|
Schedule |
No |
|
End Date |
|
Task |
1 |
|
11/03/08 |
|
Educational Meeting & Site Walk
|
2 |
|
11/19/08 |
|
Submittals Due
|
3 |
|
11/25/08 |
|
UMN Identifies Potential Best Value
|
4 |
|
12/05/08 |
|
Pre Award Kick Off Meeting
|
5 |
|
12/11/08 |
|
Pre-Award meeting
|
6 |
|
12/15/08 |
|
Anticipated Date of Award |
|
Bidding / Proposal Information |
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG. |
|
Award Information |
Vendor Name: |
|
Siemens Building Technologies |
Estimated Budget: |
|
$120,000 |
Awarded Cost: |
|
$70,440 |
Awarded Schedule: |
|
40 days |
Scope of Work: |
|
Installation of Video Surveillance & Card Access System |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|