Agronomy - Rebuild Soil Sterilizer Room |
|
Project Overview |
The project is for the removal and reconstruction of the existing soil sterilizer room in its current location in the Agronomy and Plant Genetics Building located on the St. Paul Campus of the University of Minnesota. The Soils Sterilizer Room purifies soils used in University agricultural research projects. The intent of this Technical Memorandum is to provide the background, define the requirements and construction systems to be considered for the project for replacement of the room.
|
Schedule |
No |
|
End Date |
|
Task |
1 |
|
2/27/2009 |
|
Educational Meeting & Site Walk
|
2 |
|
3/12/2009 |
|
Submittals Due
|
3 |
|
3/19/2009 |
|
UMN Identifies Potential Best Value
|
4 |
|
3/27/2009 |
|
Pre Award Kick Off Meeting
|
5 |
|
4/09/2009 |
|
Pre-Award meeting
|
6 |
|
4/13/2009 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
Prestige Builders |
Estimated Budget: |
|
$80,000 |
Awarded Cost: |
|
$79,000 |
Awarded Duration: |
|
80 days |
Scope of Work: |
|
Removal & reconstruction of the existing soil sterilizer room |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
Closeout Status |
Vendor met proposed schedule: |
|
Yes |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
10 |
| Final rating of contractor (10 max): |
|
9.6 |
|
|