University of Minnesota
Biomedical Discovery District |
|
Project Overview |
The University is requesting Proposals for services for a Design Build contract for the design and construction/installation of a new underground electrical feeder for the future Biomedical Complex in the Northeast District.
|
Schedule |
| 1 |
|
6/10/2009 |
|
Educational Meeting & Site Walk |
| 2 |
|
7/1/2009 |
|
Submittals Due |
| 3 |
|
7/14/2009 |
|
Interviews |
| 4 |
|
7/22/2009 |
|
UMN Identifies Potential Best Value |
| 5 |
|
7/28/2009 |
|
Pre Award Kick Off Meeting |
| 6 |
|
8/10/2009 |
|
Pre-Award meeting |
| 7 |
|
8/14/2009 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
Kraus-Anderson Construction |
Estimated Budget: |
|
$3,281,000 |
Awarded Cost: |
|
$3,281,000 |
Awarded Duration: |
|
390 days |
Scope of Work: |
|
Installation of a new underground electrical feeder |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|