University of Minnesota

University of Minnesota
4th Street Sprinkler System Replacement

Project Overview
Remove and dispose of existing non-galvanized sprinkler pipe, non-galvanized fittings, and couplings. Furnish and install new galvanized sprinkler piping, galvanized fittings, and grooved galvanized couplings, throughout the parking ramp that are exposed to temperature change. Provide and or replace pipe hangers when necessary. Include hydrostatic testing at 200 PSI. Maintain all existing electrical wiring, including wiring of alarm devices and alarm systems.
Schedule

No
 
End Date
 
Task
1
 
6/29/07
  Educational Meeting & Site Walk
2
 
7/17/07
  Submittals Due (Proposal, RA Plan, EEO)
3
 
7/23/07
  UMN Identifies Best Value
4
 
7/25/07
  Pre Award Kick Off Meeting
5
 
8/08/07
  Pre Award Meeting
6
 
8/10/07
  Anticipated Date of Award

Award Information
Vendor Name:
  Service Fire Protection, Inc.
Estimated Budget:
  $ 100,000
Awarded Cost:
  $ 109,710
Awarded Schedule:
  28 days
Scope of Work:
  Renovate and dispose of existing non-galvanized sprinkler pipe

For detailed award information, click here (pptico XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)

For a complete list of all project risks, click here (pptico DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.
Closeout Status
Vendor met proposed schedule:
  Yes
Vendor met proposed cost:
  Yes
Vendor met purposed quality/customer satisfaction:
  Yes
Final customer rating of PIPS (10 max):
  9
Final rating of contractor (10 max):
  10

If you have any questions please email John Savicky at John.Savicky@asu.edu