University of Minnesota
4th Street Sprinkler System Replacement |
|
Project Overview |
Remove and dispose of existing non-galvanized sprinkler pipe, non-galvanized fittings, and couplings. Furnish and install new galvanized sprinkler piping, galvanized fittings, and grooved galvanized couplings, throughout the parking ramp that are exposed to temperature change. Provide and or replace pipe hangers when necessary. Include hydrostatic testing at 200 PSI. Maintain all existing electrical wiring, including wiring of alarm devices and alarm systems.
|
|
Schedule |
No |
|
End Date |
|
Task |
1 |
|
6/29/07 |
|
Educational Meeting & Site Walk |
2 |
|
7/17/07 |
|
Submittals Due (Proposal, RA Plan, EEO) |
3 |
|
7/23/07 |
|
UMN Identifies Best Value |
4 |
|
7/25/07 |
|
Pre Award Kick Off Meeting |
5 |
|
8/08/07 |
|
Pre Award Meeting |
6 |
|
8/10/07 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
Service Fire Protection, Inc. |
Estimated Budget: |
|
$ 100,000 |
Awarded Cost: |
|
$ 109,710 |
Awarded Schedule: |
|
28 days |
Scope of Work: |
|
Renovate and dispose of existing non-galvanized sprinkler pipe |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
Closeout Status |
Vendor met proposed schedule: |
|
Yes |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
9 |
Final rating of contractor (10 max): |
|
10 |
|
|
|
|
 |