City of Peoria, AZ |
|
|
Pilot Projects - 2005 |
No |
|
|
|
|
|
1 |
Butler Water Reclamation Facility |
CMAR |
12/08/2005 |
$106,400,000 |
Completed |
2 |
Branch Library Building |
DB |
11/07/2005 |
$7,200,000 |
Awarded |
3 |
Permitting Software |
Software |
10/25/2005 |
$1,109,000 |
Awarded |
4 |
Fire Station Design Services |
A/E |
8/05/2005
|
$251,850 |
Completed |
5 |
Deer Valley Road DCR |
A/E |
6/09/2005 |
$360,420 |
Completed |
6 |
67th Ave.Widening & Drainage DCR |
A/E |
5/19/2005 |
$348,119 |
Completed |
7 |
Development Services Building |
DB |
4/05/2005 |
$20,858,000 |
Completed |
8 |
Zone 5/6 Pump Station and Reservoir |
CMAR |
4/05/2005 |
$7,078,000 |
Completed |
Total: |
$143,605,389 |
|
|
|
|
 |