City of Peoria

City of Peoria, AZ
Twin Buttes Water Treatment Plant

Project Overview
The City of Peoria is seeking a qualified Design Build Team to provide design and construction services for the new Twin Buttes Water Treatment Plant (WTP). Submitting teams will ideally possess experience in completing water treatment plant projects utilizing a design build approach, and should be able to demonstrate very high customer satisfaction from past clients from the programming phase through the end of a project's warranty period. The City of Peoria's total estimate for this project is $62 million. This includes right of way, land, permitting, and all design/build costs.

Schedule

No
 
End Date
 
Task
1
 
10/26/07
 
Pre-Submittal Conference
2
 
11/08/07
 
Submittals Due
3
 
11/16/07
 
Notification of Shortlist
4
 
11/29/07
 
Interviews* (shortlisted firms only) 
5
 
11/30/07
 
Best-Value Firm Notification
6
 
12/06/07
 
Kick-off for Pre-Award Phase
7
 
1/15/08
 
Anticipated Council Award


Bidding / Proposal Information
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG.
Award Information
Vendor Name:
  In Progress
Estimated Budget:
  In Progress
Awarded Cost:
  In Progress
Awarded Schedule:
  In Progress

If you have any questions please email John Savicky at John.Savicky@asu.edu