The scope of this project is the renovation of the fifth floor in the Sackler Museum. The project consists of the interior renovation of the fifth floor of the existing operating museum building. The critical components for this project are as follows: General Contractor, Project Manager (person), Site Supervisor (person), Millwork Subcontractor, Electrical Subcontractor, Mechanical Subcontractor. This is an in-operation building.
Bidding / Proposal Information
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG.
Award Information
Vendor Name:
  Glouceater
Estimated Budget:
  N/A
Awarded Cost:
  $411,009
Awarded Schedule:
  140 days (December 2004)
Closeout Status
Vendor met proposed schedule:
  N/A
Vendor met proposed cost:
  N/A
Vendor met purposed quality/customer satisfaction:
  N/A
Final customer rating (10 max):
  N/A