Exterior Canopies

Project Overview
The Edward Zorinsky Federal Building has a history of ice melting and falling from the sunshades and the window sills which causes an unsafe condition for pedestrians on the sidewalk. Snow guards, currently contracted under a separate work item , are being installed at the sheet metal window sills. This project should consist of a solution to remedy the problem at the sunshades and provide a safe right of way for tenants and pedestrians.

Schedule

No   End Date   Task
Pre-Construction Phase Activities
1   4/23/2010   Project Announcement / RFP Released
2   5/5/2010   Educational Meeting (See Section 1.11)
3   5/17/2010   Proposals Due (3:00 PM Kansas City Time)
4   5/20/2010   Identification of Potential Best-Value
5   5/21/2010   Kick Off Meeting
6   6/1/2010   Pre-Award Meeting
7   6/4/2010   Anticipated Award for PreConstruction Services
Construction Phase Activities
8   8/27/2010   Exercise of Construction Phase Option
9   8/27/2010   Notice to Proceed
10   12/1/10   Substantial Completion Date


Bidding / Proposal Information
All information is removed once bids are submitted. To obtain this information, please contact the client or email the PBSRG contact listed below.

If you have any questions please email Jake Smithwick at Jake.Smithwick@asu.edu
Contact Us