General Dynamics C4S
Roofing Projects |
|
Project Overview |
GDC4S is using the PIPS process to select high performing vendors for five roofs on their Scottsdale, AZ campus. The total roofing area is 107,193 sf from five (5) separate roofs. The project includes three removal and replacements with a TREMCO Cold-Applied 3-Ply Built Up Roofing System and two recoatings with TREMCO Polar Coat.
|
|
Schedule |
No |
|
End Date |
|
Task |
1 |
|
8/11/06 |
|
Educational Meeting |
2 |
|
8/11/06 |
|
Site Walk |
3 |
|
8/18/06 |
|
Contractors / Manufacturers Submit Reference Lists |
4 |
|
9/01/06 |
|
Surveys Due |
5 |
|
9/01/06 |
|
Bid Proposals Due |
6 |
|
9/01/06 |
|
Risk Assessment Plan Due |
7 |
|
9/06/06 |
|
Identification of Potential Best Value |
8 |
|
9/13/06 |
|
Pre-Award Meeting |
9 |
|
TBD |
|
Award |
|
|
Bidding / Proposal Information |
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG. |
|