Entergy
Magnolia and Tulane Campuses |
|
Schedule |
No |
|
End Date |
|
Task |
1 |
|
4/05/07 |
|
Pre-Education Meeting |
2 |
|
4/11/07 |
|
Pre-Bid Meeting / Review PIPS
|
3 |
|
5/09/07 |
|
Bids Due |
4 |
|
5/10/07 |
|
Shortlist / Identify top three prioritized contractors |
5 |
|
5/16/07 |
|
Interviews / Identification of BV |
6 |
|
5/17/07 |
|
Pre-Award Kickoff Meeting |
7 |
|
5/30/07 |
|
Project Award / NTP |
8
|
|
6/04/07 |
|
Construction Begins |
|
Bidding / Proposal Information |
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG. |
|
Award Information |
Vendor Name: |
|
MAPP Construction |
Estimated Budget: |
|
$10,000,000 |
Awarded Cost: |
|
$3,077,438 |
|
|
Closeout Status |
Vendor met proposed schedule: |
|
Yes |
Vendor met proposed cost: |
|
Yes |
|
|