Entergy

Entergy
Magnolia St. Bldg. 529 Flr.1 Restorations

Schedule

No
 
End Date
 
Task
1
 
11/07/06
 
Pre-bid meeting @ 1:30pm
2
 
11/16/05
 
Bid Due @ 2:00pm
3
 
11/17/06
 
Best-Value Contractor Preliminary Selection
4
 
11/20/06
 
Pre-Kickoff Meeting
5
 
11/29/06
 
Pre-Planning Meeting Presentation
6
 
12/01/06
 
Award Contract
7
 
1/29/07
 
Project Completion


Bidding / Proposal Information
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG.
Award Information
Vendor Name:
  Chartier Construction
Estimated Budget:
  $200,000
Awarded Cost:
  $162,950
Closeout Status
Vendor met proposed schedule:
  Yes
Vendor met proposed cost:
  Yes

If you have any questions please email John Savicky at John.Savicky@asu.edu