City of Rochester's first PIPS process is the construction of a new Public Works and Transit Operations Center in northeast Rochester. This project consists of a main operations building with offices, a fleet parking garge, adjacent vehicle repair bays, workshops, and storage areas. Seperate structures for wash and fuel operations, equipment storage and material storage along with all site pavements and ground covers.
|
Schedule |
| 1 |
|
12/14/09 |
|
Project Announcement |
| 2 |
|
1/05/10 |
|
Site Tour |
| 3 |
|
1/21/10 |
|
Proposals due |
| 4 |
|
2/2/10 |
|
Interviews |
| 5 |
|
2/03/10 |
|
Kick-Off meeting |
| 6 |
|
3/9/10 |
|
Pre-Award Meeting |
| 7 |
|
3/17/2010 |
|
Anticipated Notice to Proceed Date |
| 8 |
|
4/2010 |
|
Construction Start Date |
| 9 |
|
6/2011 |
|
Final Completion Date |
|
Bidding / Proposal Information |
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG. |
|
Award Information |
Vendor Name: |
|
Alvin E. Benike, Inc. |
Estimated Budget: |
|
$28.5 Million |
Awarded Cost: |
|
$22,675,162 |
Awarded Duration: |
|
441 days |
Scope of Work: |
|
New construction of Public Works and Transit Operations. |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|