Rochester Public Works & Transit Operations
(Electrical)

Project Overview

Complete construction of the ELECTRICAL TECHNOLOGY PACKAGE at the new Public Works and Transit Operations Center. This project consists of a main operations building with offices, a fleet parking garage, adjacent vehicle repair bays, workshops, and storage areas. Additional work associated with separate on site structures for wash and fuel operations, equipment and material storage, and site improvements.

Major Work: “Voice Data/ Video Structured cabling systems, paging and Intercom System, CATV Cabling system and Security System”.


Schedule

No   End Date   Task
1   06/08/2010   Pre Proposal/ Best Value Trainning (Mandatory)
2   06/23/2010   Submittals Due
3   06/29/2010   Notification of Shortlist
4   06/30/2010   Interviews (if conducted)
5   07/01/2010   Pre-Award Kickoff Meeting
6   07/26/2010   Final Pre-Award Meeting
7   08/02/2010   Project Award

Award Information
Vendor Name:
  All Systems Installation, Inc.
Estimated Budget:
  $400,000
Awarded Cost:
  $357,325
Awarded Duration:
  150 Days
Scope of Work:
  Electrical Technology Package

For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)

For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.

If you have any questions please email Anthony Perrenoud at aperreno@exchange.asu.edu