Arizona School Facilities Board
Glendale Union HSD Smoke Detectors |
|
Project Background |
- GC was not finishing the work
- Fire sprinkler systems were worked on by multiple contractors
- No one knew exactly what work had been done
- No one had design plans for the systems
- Operating system can only be worked on by Seimen’s certified contractor
- Multiple Government Agencies were involved
|
Procurement Problems |
- Fast Track Project
- 1.5 months to solicit and award contract
- High Risk Project
- No contractors wanted to Bid project
- Low Budget
- SFB had very little funds
|
Award Information |
Vendor Name: |
|
Millennium 3 Technologies |
Award Price: |
|
$430,000 |
Duration: |
|
180 days |
|
Results of Selection
- Construction Cost reduced by $530,000 through engineering analysis and site investigation
- Contractor learned to install new wireless system
- All government parties coordinated with
- All permits and approvals received
- In depth Risk Minimization plans created
Project Results
|
Vendor met proposed schedule: |
|
Yes |
Vendor met proposed cost:
|
|
Yes ($22,000 modification due to additional
device testing requirement by the State) |
Final customer rating (10 max): |
|
10 |
|
|