Arizona State University
Packard Drive North Parking Structure - Design |
|
Project Overview |
ASU is seeking a qualified designer to provide design services for a parking garage and office building. The university has roughly estimated the need for a ±1,600 stall parking structure; an up to 30,000gsf office building; a 20,000 – 30,000gsf pedestrian mall; and to reach the highest feasible level of LEED certification. The project will be constructed under the CMAR delivery method. It is ASU’s strong desire to have the parking structure aspect completed by August 1, 2010, to be fully functional for the 2010 football season.
|
Schedule |
No |
|
End Date |
|
Task |
1 |
|
6/19/08 |
|
Designer RFP Released
|
2 |
|
6/26/08 |
|
Designer Pre-Proposal Education Session
|
3 |
|
7/24/08 |
|
Past Performance Surveys Due (3:00pm MST)
|
4 |
|
7/24/08 |
|
Designer Proposals Due (3:00pm MST)
|
5 |
|
7/29/08 |
|
Designer Shortlisting (if necessary)
|
6 |
|
8/5/08 |
|
Designer Interviews
|
7 |
|
8/6/08 |
|
Designer Best Value Selection
|
8 |
|
8/11/08 |
|
Designer Pre-Award QC Kickoff Education
|
9 |
|
-- |
|
Designer Pre-Award Period
|
10 |
|
8/28/08 |
|
Designer Pre-Award Summary Meeting
|
11 |
|
8/29/08 |
|
Designer Award |
|
Bidding / Proposal Information |
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG. |
|
Award Information |
Designer: |
|
Architekton |
Estimated Budget: |
|
$3,000,000 |
Awarded Cost: |
|
$2,972,000 |
Awarded Schedule: |
|
371 calendar days |
|
|